Home »
MCQs »
Engineering Subjects MCQs
Estimating and Costing MCQs (Multiple-Choice Questions) and Answers
This section contains multiple-choice questions and answers on Estimating and Costing in Civil Engineering and its various topics such as Introduction, Elements of Building Estimate, Estimate of Buildings, Reinforced Cement Concrete Works, Wood Work for Doors and Windows, Water Supply and Sanitary Works, Sloped Roof, Roof Truss, and Steel Structures, Irrigation Works, and more. Practice these Estimating and Costing MCQs to learn and enhance your skills in Estimating and Costing.
Estimating and Costing MCQs with Answers and Explanations
Here are the top multiple-choice questions and answers on estimating and costing MCQs:
1. What is the purpose of estimating in civil engineering?
- To precisely determine project costs
- To forecast potential project expenses
- To ensure regulatory compliance
- To monitor project progress
Answer: B) To forecast potential project expenses
Explanation:
Estimating helps forecast potential project expenses by analyzing various factors such as materials, labor, and equipment costs.
Discuss this question
2. Which estimating technique relies on historical data from similar projects to estimate costs?
- Bottom-up estimating
- Three-point estimating
- Analogous estimating
- Parametric estimating
Answer: C) Analogous estimating
Explanation:
Cost estimates from comparable projects are based on past data when using analogous estimation.
Discuss this question
3. Which estimate involves the assessment of quantities of materials required for construction, such as concrete, steel, or bricks?
- Quantity estimate
- Supplementary estimate
- Detailed estimate
- Revised estimate
Answer: A) Quantity estimate
Explanation:
Determine the amounts of different building materials required based on project specifications and drawings. This process is known as quantity surveying or quantity estimation.
Discuss this question
4. When a project undergoes significant changes, leading to adjustments in its cost, which type of estimate is prepared to reflect these alterations?
- Revised estimate
- Quantity estimate
- Complete estimate
- Preliminary estimate
Answer: A) Revised estimate
Explanation:
Revised estimates are prepared when substantial changes occur in a project, necessitating adjustments to the initial cost estimations to reflect the new scope or requirements.
Discuss this question
5. Which type of estimate is prepared when additional work beyond the original project scope is required, leading to an increase in project costs?
- Detailed estimate
- Supplementary estimate
- Preliminary estimate
- Quantity estimate
Answer: B) Supplementary estimate
Explanation:
When unexpected events or more work crop up throughout the building process, supplemental estimates are made to account for them, which drives up project prices.
Discuss this question
6. Which type of estimate is prepared with detailed item-wise calculations and measurements, offering a precise breakdown of all project expenses?
- Preliminary estimate
- Revised estimate
- Quantity estimate
- Detailed estimate
Answer: D) Detailed estimate
Explanation:
Detailed estimates provide itemized calculations and measurements for all project expenses, offering a precise breakdown of costs for each component involved in construction.
Discuss this question
7. Which type of estimate provides a detailed breakdown of all project costs?
- Revised estimate
- Quantity estimate
- Complete estimate
- Preliminary estimate
Answer: C) Complete estimate
Explanation:
All project costs, including those for supplies, labor, equipment, and overhead, are broken out in detail in the complete estimate.
Discuss this question
8. Which type of estimate is prepared to account for ongoing maintenance expenses?
- Quantity estimate
- Preliminary estimate
- Annual maintenance estimate
- Complete estimate
Answer: C) Annual maintenance estimate
Explanation:
An annual maintenance estimate is prepared to account for ongoing maintenance expenses associated with a construction project or facility.
Discuss this question
9. In detailed estimating, which factor is influenced by local labor charges?
- Availability of materials
- Quality control measures
- Project duration
- Equipment rental rates
Answer: C) Project duration
Explanation:
Project duration is influenced by local labor charges, as higher labor costs may extend the duration of the project, thus impacting the overall cost estimation.
Discuss this question
10. Which factor is directly influenced by local labor charges during cost estimation?
- Site topography
- Material quality
- Worker safety measures
- Project budget
Answer: D) Project budget
Explanation:
The project budget is directly impacted by local labor charges, as higher labor costs can significantly affect the overall project cost estimation.
Discuss this question
11. When estimating transportation costs for materials, what is essential to consider?
- Site aesthetics
- Road infrastructure
- Environmental regulations
- Nearby tourist attractions
Answer: B) Road infrastructure
Explanation:
Road infrastructure is critical to consider for estimating transportation costs, as poor road conditions or lack of access routes can increase transportation expenses.
Discuss this question
12. When preparing a detailed estimate, what should be considered regarding the availability of materials?
- Distance to the nearest hospital
- Site security measures
- Source reliability
- Proximity to educational institutions
Answer: C) Source reliability
Explanation:
Source reliability is crucial for estimating costs, as unreliable material sources can lead to delays and increased expenses during construction.
Discuss this question
13. In earthwork filling, what does compaction primarily affect?
- The organic content
- The moisture content
- The density of the soil
- The color of the soil
Answer: C) The density of the soil
Explanation:
By decreasing air spaces, compaction raises the density of the soil, improving its strength and stability.
Discuss this question
14. Why is shoring required during excavation?
- To decorate the site
- To drain water from the site
- To support the soil and prevent collapse
- To mix concrete
Answer: C) To support the soil and prevent collapse
Explanation:
To keep the area safe and prevent collapses, shoring temporarily supports the earth around excavations.
Discuss this question
15. What is the key consideration when estimating brickwork in arches?
- Color of the bricks
- Type of mortar used
- Weight of each brick
- Radius and number of bricks in the arch
Answer: D) Radius and number of bricks in the arch
Explanation:
Estimating brickwork in arches involves calculating the radius and the number of bricks required to form the curved structure accurately.
Discuss this question
16. Where is honeycomb brickwork typically used?
- For decorative purposes only
- In the construction of retaining walls
- For underwater structures
- In walls requiring ventilation and reduced weight
Answer: D) In walls requiring ventilation and reduced weight
Explanation:
Honeycomb brickwork is used where ventilation is needed, such as in boundary walls, and where reducing the weight of the wall is beneficial.
Discuss this question
17. What is the main purpose of brick flat soling?
- To provide a smooth surface
- To serve as a base for flooring
- To prevent water seepage
- To add decorative elements
Answer: B) To serve as a base for flooring
Explanation:
Brick flat soling is used to provide a firm and level base for laying floors, enhancing the stability and strength of the floor above.
Discuss this question
18. Which phase of a project typically requires the highest degree of accuracy in cost estimating?
- Preliminary design phase
- Conceptual design phase
- Detailed design phase
- Feasibility study phase
Answer: C) Detailed design phase
Explanation:
During the detailed design phase, the project scope and specifications are well-defined, requiring a higher degree of accuracy to ensure precise cost estimation.
Discuss this question
19. What is a common method used to improve the degree of accuracy in estimating costs?
- Using rough estimates
- Ignoring contingency factors
- Relying on past project data only
- Applying standard unit costs and detailed quantity take-offs
Answer: D) Applying standard unit costs and detailed quantity take-offs
Explanation:
Detailed quantity take-offs and the application of standard unit costs lead to more accurate and reliable cost estimates.
Discuss this question
20. Which tool or technique is often used to ensure a higher degree of accuracy in cost estimates for large projects?
- Simple averaging
- Parametric estimating
- Analogous estimating
- Rough order of magnitude estimating
Answer: B) Parametric estimating
Explanation:
Parametric estimating uses statistical relationships between historical data and other project variables to enhance the accuracy of cost estimates for large projects.
Discuss this question
21. Which factor does NOT significantly influence the degree of accuracy in cost estimation?
- Color of the project documents
- Experience and expertise of the estimator
- Variability of material costs
- Quality of the project design
Answer: A) Color of the project documents
Explanation:
The color of the project documents does not influence the accuracy of cost estimation. The other factors listed are critical to achieving accurate estimates.
Discuss this question
22. Which of the following is a potential consequence of a low degree of accuracy in cost estimating?
- Enhanced project performance
- Increased stakeholder confidence
- Significant cost overruns
- Reduced project scope
Answer: C) Significant cost overruns
Explanation:
Budget problems and possible project delays might arise from cost overruns caused by inaccurate cost estimation.
Discuss this question
23. Which method is commonly used when the walls are of varying thickness and lengths?
- Centre Line Method
- Long and Short Wall Method
- Crossing Method
- Out to Out and In to In Method
Answer: B) Long and Short Wall Method
Explanation:
This method accommodates walls of different thicknesses and lengths, ensuring precision in the estimation process.
Discuss this question
24. Which method is particularly useful for buildings with symmetrical and repetitive structures?
- Long and short wall method
- Centre line method
- Crossing method
- None of the above
Answer: C) Crossing method
Explanation:
The Centre line method is effective for symmetrical and repetitive structures because it allows for simpler calculations.
Discuss this question
25. The crossing method is primarily used for estimating which type of structural element.
- Foundations
- Beams and columns
- Roofs
- Walls
Answer: B) Beams and columns
Explanation:
The crossing method is often used for beams and columns where intersecting lines can simplify calculations.
Discuss this question
26. Which type of foundation is most suitable for a residential building on stable, level ground?
- Pile foundation
- Raft foundation
- Strip foundation
- Floating foundation
Answer: C) Strip foundation
Explanation:
Since they offer sufficient support for the load-bearing walls, strip foundations are frequently utilized for residential structures on flat, stable terrain.
Discuss this question
27. Which material is primarily used for roofing in modern residential construction due to its durability and weather resistance?
- Asphalt shingles
- Clay tiles
- Thatch
- Metal sheets
Answer: D) Metal sheets
Explanation:
Metal roofing sheets are a common choice due to their extended lifespan, tolerance to weather, and durability.
Discuss this question
28. Which type of foundation is typically used for buildings on weak soil?
- Strip foundation
- Pad foundation
- Raft foundation
- Pile foundation
Answer: D) Pile foundation
Explanation:
To shift the weight to deeper, more stable strata in poor soil, pile foundations are utilized.
Discuss this question
29. What is the primary function of a roof truss in construction?
- Moisture resistance
- Structural support
- Aesthetic design
- Thermal insulation
Answer: B) Structural support
Explanation:
The structural support required to support the weight of the roof and move it to the walls is provided by roof trusses.
Discuss this question
30. Which material is most commonly used for wall putty?
- Polyurethane
- Gypsum
- Lime
- Cement
Answer: B) Gypsum
Explanation:
Gypsum-based wall putty is widely used to create a smooth and even surface before painting.
Discuss this question
31. What type of hinge is typically used for doors to ensure smooth operation?
- Butt hinge
- Concealed hinge
- Pivot hinge
- Continuous hinge
Answer: A) Butt hinge
Explanation:
Butt hinges are commonly used for doors due to their simplicity and effective functionality.
Discuss this question
32. In estimating the cost of bricks for a pump house, which of the following factors is the least likely to affect the cost per brick?
- Cost of transportation
- Location of the construction site
- Type of bonding used in brickwork
- Size of the bricks
Answer: C) Type of bonding used in brickwork
Explanation:
The type of bonding affects the overall amount of mortar and labor but not the cost per individual brick directly.
Discuss this question
33. What is the purpose of adding a wastage percentage in material estimation?
- To cover unexpected project delays
- To account for damaged or unusable materials
- To provide a safety margin for labor costs
- To adjust for changes in material prices
Answer: B) To account for damaged or unusable materials
Explanation:
Adding wastage percentage ensures that the estimated materials cover any potential losses due to breakage or errors.
Discuss this question
34. What factor is most critical when estimating the cost of cement for mortar in a pump house?
- Cement brand
- Cement grade
- Mixing technique
- Distance from the cement plant
Answer: B) Cement grade
Explanation:
The grade of cement determines its strength and suitability for construction, which directly impacts the cost.
Discuss this question
35. Which of the following costs is not typically included in the direct costs of constructing a pump house?
- Material costs
- Equipment rental
- Labor costs
- Project management fees
Answer: D) Project management fees
Explanation:
Project management fees are considered indirect costs as they are not directly tied to the physical construction process.
Discuss this question
36. What is the main advantage of using High Alumina Cement in construction?
- Low cost
- Low heat of hydration
- High availability
- Rapid setting and high early strength
Answer: D) Rapid setting and high early strength
Explanation:
High Alumina Cement offers a rapid setting and high early strength, making it advantageous for time-sensitive projects.
Discuss this question
37. Which type of cement is most commonly used in general construction applications where a moderate rate of setting and strength development is sufficient?
- Normal-setting Portland cement
- Quick-setting Portland cement
- Low-heat Portland cement
- Rapid-hardening Portland cement
Answer: A) Normal-setting Portland cement
Explanation:
Normal-setting Portland cement is the standard choice for most general construction projects, offering a balanced combination of setting time, strength development, and versatility.
Discuss this question
38. Which type of cement is suitable for applications requiring reduced heat generation during hydration, such as in massive foundation elements?
- Normal setting Portland cement
- Quick-setting Portland cement
- Low-heat Portland cement
- Rapid-hardening Portland cement
Answer: C) Low-heat Portland cement
Explanation:
Low-temperature Portland cement is perfect for large concrete parts where excessive heat buildup can cause cracking since it is specially engineered to limit heat output during hydration.
Discuss this question
39. Which type of aggregate is derived from natural sources and has not been subjected to any artificial process?
- Manufactured aggregate
- Synthetic aggregate
- Natural aggregate
- Recycled aggregate
Answer: C) Natural aggregate
Explanation:
Quarries, pits, and rivers are examples of naturally occurring sources from which natural aggregates can be derived.
Discuss this question
40. In aggregate grading, what does the term 'maximum size' refer to?
- The smallest particle size in the aggregate mix
- The largest particle size in the aggregate mix
- The size of the aggregate container
- The average particle size in the aggregate mix
Answer: B) The largest particle size in the aggregate mix
Explanation:
The maximum size indicates the largest particle size present in the aggregate mix.
Discuss this question
41. In concrete mix design, what effect does a poorly graded aggregate have on the final product?
- Decreased workability and increased water demand
- Enhanced bond strength with reinforcement
- Reduced bleeding and segregation
- Improved strength and durability
Answer: A) Decreased workability and increased water demand
Explanation:
Poorly graded aggregate can result in decreased workability and increased water demand in concrete mixes.
Discuss this question
42. In the context of estimating costs, what does the term 'material proportion' refer to?
- The ratio of materials used in a construction mix
- The weight of materials about the total project weight
- The quantity of materials required for a specific project
- The cost of materials per unit volume
Answer: A) The ratio of materials used in a construction mix
Explanation:
The relative amounts of various components, such as aggregate, sand, and cement, in a mixture are referred to as material proportion.
Discuss this question
43. In estimating costs for a project, why is it important to accurately determine material proportions?
- To simplify procurement processes
- To minimize waste and optimize resources
- To comply with building regulations
- To ensure structural stability
Answer: B) To minimize waste and optimize resources
Explanation:
Accurate material proportions help in efficient resource utilization, minimizing waste and cost overruns.
Discuss this question
44. Which of the following factors does not affect the bulking of sand?
- Moisture content
- Particle shape
- Compaction effort
- Particle size distribution
Answer: C) Compaction effort
Explanation:
Compaction effort refers to the energy applied during compaction, which is not directly related to the bulking phenomenon.
Discuss this question
45. What precautions should be taken while estimating the quantity of bulking sand for construction projects?
- Ignore the bulking factor to avoid overestimation
- Account for the bulking factor to avoid underestimation
- Adjust bulking factor based on particle shape
- Use bulking factor only for fine sand
Answer: B) Account for the bulking factor to avoid underestimation
Explanation:
It's essential to consider the bulking factor while estimating sand quantity to ensure accurate project planning and material procurement.
Discuss this question
46. Which of the following parameters is NOT typically used to assess the quality of water for construction purposes?
- pH level
- Total Dissolved Solids
- Turbidity
- Air pressure
Answer: D) Air pressure
Explanation:
Air pressure does not directly relate to water quality assessment for construction.
Discuss this question
47. What does a high slump value indicate during the Slump Test?
- Low workability
- Excessive water content
- Proper proportion of aggregates
- Insufficient mixing time
Answer: B) Excessive water content
Explanation:
A high slump number indicates that there may be too much water in the concrete mix, which might result in less durable and strong concrete.
Discuss this question
48. What is the recommended number of layers for rodding the concrete during the Slump Test?
- One layer
- Two layers
- Three layers
- Four layers
Answer: C) Three layers
Explanation:
ASTM guidelines recommend rodding the concrete in three equal layers to ensure proper compaction and accurate slump measurement.
Discuss this question
49. What is the term for the process of ensuring proper end anchorage of reinforcement bars during construction?
- Bar splicing
- Bar bending
- Bar lapping
- Bar hooking
Answer: A) Bar splicing
Explanation:
Bar splicing refers to the process of securely connecting reinforcement bars, including ensuring proper end anchorage, during construction to maintain the structural integrity of the concrete.
Discuss this question
50. Which of the following factors does not influence the cost estimation of door and window frames?
- Material type
- Paint color
- Frame dimensions
- None of the above
Answer: B) Paint color
Explanation:
While paint color may affect the overall appearance, it typically does not significantly impact the cost estimation of door and window frames.
Discuss this question
51. In the context of cost estimation, what does the term "joinery" refer to regarding door and window frames?
- Material selection
- Installation labor
- Painting process
- Woodwork detailing
Answer: D) Woodwork detailing
Explanation:
Joinery refers to the detailed woodworking involved in crafting door and window frames, which affects the overall cost.
Discuss this question
52. What is the purpose of providing a sill in a window frame?
- Thermal insulation
- Aesthetic enhancement
- Weatherproofing
- Structural support
Answer: C) Weatherproofing
Explanation:
The sill in a window frame helps to prevent water ingress and ensures proper drainage, contributing to weatherproofing.
Discuss this question
53. Which of the following is NOT typically included in the cost estimation of a battened ledged door leaf?
- Hardware such as locks and handles
- Labor charges for installation
- Transportation costs
- Cost of land for construction
Answer: D) Cost of land for construction
Explanation:
The cost of land is not directly related to the construction of a door leaf and thus not included in its estimation.
Discuss this question
54. Which method is commonly used for estimating the cost of a battened ledged door leaf?
- Comparative method
- Unit method
- Cubic method
- Area method
Answer: B) Unit method
Explanation:
The unit method, which involves estimating costs based on standard units of measurement, is commonly used for door leaf cost estimation.
Discuss this question
55. When estimating the cost of a battened ledged door leaf, why is it important to consider the door dimensions?
- To determine the number of hinges required
- To calculate the amount of paint needed
- To assess the overall project budget
- To accurately determine material quantities
Answer: D) To accurately determine material quantities
Explanation:
Door dimensions directly impact the quantity of materials required for construction, hence influencing cost estimation.
Discuss this question
56. When estimating the cost of a parallel door shutter, why is it important to account for wastage?
- To ensure precise measurements
- To minimize material and cost wastage
- To increase the durability of the door shutter
- To speed up the construction process
Answer: B) To minimize material and cost wastage
Explanation:
Accounting for wastage helps in optimizing material usage and reducing unnecessary expenses during construction.
Discuss this question
57. Which method is commonly used for estimating the cost of a parallel door shutter?
- Market survey
- Trial and error
- Random selection
- Guesswork
Answer: A) Market survey
Explanation:
Conducting a market survey involves gathering information on the prices of materials and labor in the current market, which is a standard method for estimating costs.
Discuss this question
58. Which factor is NOT typically considered when estimating the cost of a Venetian window shutter?
- Installation complexity
- Type of material used
- Manufacturer's warranty
- Size of the window
Answer: C) Manufacturer's warranty
Explanation:
While the manufacturer's warranty may influence the overall decision, it is not directly factored into the estimation of the shutter cost.
Discuss this question
59. Which method is commonly used to estimate the cost of a Venetian window shutter?
- Market analysis
- Quantity takeoff
- Risk assessment
- Value engineering
Answer: B) Quantity takeoff
Explanation:
Quantity takeoff involves calculating the quantity of materials required and multiplying it by their respective unit costs to estimate the total cost.
Discuss this question
60. Which stage of the construction process is most suitable for estimating the cost of a glazed window shutter?
- Pre-construction phase
- Design development phase
- Post-construction phase
- Construction phase
Answer: B) Design development phase
Explanation:
Estimating costs during the design development phase allows for early budget planning and adjustments to the design if necessary to meet budget constraints.
Discuss this question
61. Which window fitting is designed to allow ventilation while preventing insects from entering?
- Window latch
- Window screen
- Window hinge
- Window stopper
Answer: B) Window screen
Explanation:
Mesh covers called window screens are put over windows to let in air while keeping insects out.
Discuss this question
62. What window fitting is used to facilitate easy opening and closing of a window sash?
- Window stopper
- Window hinge
- Window latch
- Window handle
Answer: D) Window handle
Explanation:
Window handles are mechanisms attached to window sashes to allow users to open and close them with ease.
Discuss this question
63. What does IS 200 cover in the context of civil engineering?
- Design principles for bridges
- Guidelines for road construction
- Standards for electrical installations
- Method of measurement for water supply and sanitary works
Answer: D) Method of measurement for water supply and sanitary works
Explanation:
IS 200 specifically outlines the method of measurement for water supply and sanitary works in civil engineering projects.
Discuss this question
64. According to IS 200, what is the purpose of measuring water supply and sanitary works?
- To assess the environmental impact
- To calculate labor costs only
- To determine the total cost of the project
- To estimate material costs only
Answer: C) To determine the total cost of the project
Explanation:
Measurement of water supply and sanitary works helps in determining the overall cost of the construction project.
Discuss this question
65. Which of the following is NOT covered under water supply and sanitary works according to IS 200?
- Installation of water tanks
- Fitting of bathroom fixtures
- Construction of swimming pools
- Laying of sewer pipes
Answer: C) Construction of swimming pools
Explanation:
Swimming pool construction is not typically included under water supply and sanitary works as defined by IS 200.
Discuss this question
66. In IS 200, what are Effluent Drains primarily used for?
- Transporting drinking water
- Disposing of industrial waste
- Filtering rainwater
- Irrigating agricultural fields
Answer: B) Disposing of industrial waste
Explanation:
Effluent Drains are designed to dispose of industrial waste according to IS 200 standards.
Discuss this question
67. In estimating costs for a construction project, what does a memory well primarily rely on?
- Advanced software algorithms
- Comprehensive project documentation
- Previous project experience
- High-speed internet connection
Answer: C) Previous project experience
Explanation:
Memory well heavily depends on the experience gained from previous projects, enabling estimators to make informed decisions.
Discuss this question
68. What strategies can enhance the memory well of a civil engineer in estimating costs?
- Increasing caffeine intake
- Attending cost estimation workshops
- Practicing mnemonic techniques
- Regular physical exercise
Answer: C) Practicing mnemonic techniques
Explanation:
Mnemonic techniques, such as visualization or chunking, can aid in improving memory retention for cost estimation purposes.
Discuss this question
69. Which of the following tools is commonly used for tracking project timelines in civil engineering?
- Cost estimation software
- Gantt charts
- Concrete mix design calculators
- Structural analysis software
Answer: B) Gantt charts
Explanation:
Civil engineers frequently use Gantt charts to visually describe project deadlines and monitor progress over time.
Discuss this question
70. What is the purpose of memory well in estimating costs?
- To store historical data
- To track project progress
- To facilitate accurate cost estimation
- To organize project documentation
Answer: C) To facilitate accurate cost estimation
Explanation:
Memory well helps in storing and retrieving relevant data that aids in making accurate cost estimations for construction projects.
Discuss this question
71. Which factor is NOT typically considered when tracking project timelines in civil engineering?
- Labor productivity
- Material availability
- Weather conditions
- Project profitability
Answer: D) Project profitability
Explanation:
Project profitability is not directly related to tracking project timelines, as it primarily concerns financial aspects such as costs and revenues.
Discuss this question
72. What is a Yard Gully primarily used for in civil engineering?
- Stormwater drainage
- Sewage disposal
- Electrical conduit protection
- Foundation reinforcement
Answer: A) Stormwater drainage
Explanation:
Yard Gullies are designed to collect and divert excess rainwater away from building foundations, preventing waterlogging and potential structural damage.
Discuss this question
73. Which of the following is NOT a potential problem associated with Yard Gullies?
- Corrosion
- Blockages
- Infiltration of tree roots
- Soil compaction
Answer: D) Soil compaction
Explanation:
Soil compaction is not typically a direct problem associated with Yard Gullies; however, it may indirectly affect their performance if proper backfilling and compaction procedures are not followed.
Discuss this question
74. What is the purpose of a rodding eye in a Yard Gully?
- To increase structural integrity
- To facilitate cleaning and maintenance
- To regulate water flow
- To enhance aesthetic appeal
Answer: B) To facilitate cleaning and maintenance
Explanation:
A rodding eye allows for easy access to the Yard Gully for cleaning, maintenance, and clearing of any blockages that may occur over time.
Discuss this question
75. Which of the following factors is NOT typically considered when estimating the cost of a sloped roof with asbestos cement sheet roof covering?
- Area of the roof
- Slope of the roof
- Type of fasteners used
- Color of the asbestos cement sheets
Answer: D) Color of the asbestos cement sheets
Explanation:
The color of the asbestos cement sheets usually does not affect the cost estimation process.
Discuss this question
76. What is the primary purpose of estimating the cost of a sloped roof with Mangalore tiles roof covering?
- To determine the quantity of materials required
- To assess the overall project budget
- To calculate the labor costs involved
- All of the above
Answer: D) All of the above
Explanation:
Estimating the cost helps in determining material quantities, labor expenses, and the overall budget for the construction project.
Discuss this question
77. Which of the following factors is crucial for accurately estimating the cost of a sloped roof with Mangalore tiles?
- Roof pitch
- Roof orientation
- Type of underlayment
- Tile color
Answer: A) Roof pitch
Explanation:
The roof pitch significantly impacts material quantities and labor requirements, thus influencing the overall cost estimation.
Discuss this question
78. What role does the type of underlayment play in estimating the cost of a sloped roof with Mangalore tiles?
- It affects the aesthetics of the roof
- It has no significant impact on the cost estimation
- It impacts the cost of materials and installation
- It determines the durability of the roof
Answer: C) It impacts the cost of materials and installation
Explanation:
Different types of underlayment vary in cost, affecting the overall estimation of the roof construction project.
Discuss this question
79. When estimating the cost of a sloped roof with Mangalore tiles, which cost component is typically higher?
- Material cost
- Overhead cost
- Equipment cost
- Labor cost
Answer: A) Material cost
Explanation:
Material cost, including tiles, underlayment, and fasteners, often constitutes a significant portion of the total cost estimation.
Discuss this question
80. Which method is commonly used for estimating the quantity of Mangalore tiles required for a sloped roof?
- Area method
- Volume method
- Length method
- Weight method
Answer: A) Area method
Explanation:
The area method calculates the quantity of tiles based on the total roof area to be covered.
Discuss this question
81. Which type of truss is characterized by its triangular shape and diagonal members sloping towards the center?
- Fink truss
- Gambrel truss
- Warren truss
- Pratt truss
Answer: A) Fink truss
Explanation:
Fink trusses feature a triangular shape with diagonal members sloping towards the center, providing stability and support
Discuss this question
82. Which factor primarily influences the design of a trussed roof?
- Architectural style
- Local climate conditions
- Roof span
- Material availability
Answer: C) Roof span
Explanation:
The span of the roof determines the size and configuration of the trusses required to support the structure effectively.
Discuss this question
83. What is the primary purpose of using G.I. sheets as a roof cover?
- Aesthetic enhancement
- Structural support
- Thermal insulation
- Weather protection
Answer: D) Weather protection
Explanation:
G.I. sheets provide effective protection against weather elements such as rain, sun, and wind.
Discuss this question
84. What is an approximate estimate used for civil engineering?
- Precise budgeting
- Rough cost estimation
- Detailed project planning
- Structural analysis
Answer: B) Rough cost estimation
Explanation:
An approximate estimate provides a rough estimation of project costs at the initial stages, aiding in preliminary budgeting and decision-making.
Discuss this question
85. Which of the following factors is NOT considered when making an approximate estimate for a steel frame truss?
- Equipment costs
- Labor costs
- Material costs
- Detailed structural analysis
Answer: D) Detailed structural analysis
Explanation:
Approximate estimates typically do not involve detailed structural analysis but focus on material, labor, and equipment costs.
Discuss this question
86. Which stage of project planning typically requires an approximate estimate?
- Conceptual design
- Detailed design
- Post-construction evaluation
- Construction
Answer: A) Conceptual design
Explanation:
Approximate estimates are crucial during the conceptual design stage to assess project feasibility and budget constraints.
Discuss this question
87. Which factor has the most significant influence on the cost estimation of a grillage foundation?
- Local construction regulations
- Soil bearing capacity
- Reinforcement requirements
- Foundation depth
Answer: C) Reinforcement requirements
Explanation:
The amount and type of reinforcement needed for a grillage foundation have a significant impact on its cost, as it directly influences material and labor expenses.
Discuss this question
88. Which type of canal construction involves digging the entire canal route below ground level?
- Canal fully in excavation
- Canal with lining
- Canal fully in embankment
- None of the above
Answer: A) Canal fully in excavation
Explanation:
In a canal fully in excavation, the entire canal is dug below ground level to create the desired channel.
Discuss this question
89. Which factor significantly influences the estimation of Earthwork in canals?
- Length of the canal
- Soil type and its properties
- Depth of water flow in the canal
- Availability of construction equipment
Answer: B) Soil type and its properties
Explanation:
Soil type affects excavation and embankment processes, impacting the volume of earthwork required.
Discuss this question
90. What is the primary purpose of abstracting in quantity surveying?
- To summarize detailed measurements
- To conduct site inspections
- To create architectural drawings
- To estimate project timelines
Answer: A) To summarize detailed measurements
Explanation:
Abstracting involves summarizing detailed measurements of materials, labor, and other resources required for construction projects.
Discuss this question
91. Which method is commonly employed to estimate the volume of earthwork in canals?
- Cross-section method
- Satellite imagery analysis
- Trial and error method
- Ground-penetrating radar
Answer: A) Cross-section method
Explanation:
The cross-section method involves dividing the canal into segments and calculating the volume of earthwork for each segment.
Discuss this question
92. Which factor is NOT typically considered when estimating the cost of an R.C.C. Spun Pipe sluice?
- Material cost
- Labor cost
- Equipment cost
- Weather conditions
Answer: D) Weather conditions
Explanation:
Weather conditions may affect construction timelines; they are not directly factored into cost estimates.
Discuss this question
93. What is a hume pipe syphon primarily used for in civil engineering?
- Stormwater drainage
- Cable ducting
- Sewage disposal
- Irrigation purposes
Answer: C) Sewage disposal
Explanation:
Hume pipe syphons are commonly employed for conveying sewage under obstacles such as rivers, canals, or roads.
Discuss this question
94. Which type of measurement is commonly used in preparing Bills of Quantities?
- Gross measurement
- Net measurement
- Dimensional measurement
- Approximate measurement
Answer: B) Net measurement
Explanation:
Net measurement is commonly used in preparing Bills of Quantities, where only the actual usable quantity of materials is measured, excluding any wastage.
Discuss this question
95. Which stage of the construction project is the Bill of Quantities typically prepared?
- Design stage
- Execution stage
- Planning stage
- Completion stage
Answer: A) Design stage
Explanation:
Working on architectural drawings and requirements, the Bill of Quantities is usually created during the design phase of a building project.
Discuss this question
96. What is the purpose of including a priced Bill of Quantities in tender documents?
- To provide a list of contractors
- To facilitate cost estimation
- To identify construction materials
- To determine project timelines
Answer: B) To facilitate cost estimation
Explanation:
Provided that bidding papers include a priced Bill of Quantities, contractors can submit competitive bids and precisely estimate project costs.
Discuss this question
97. Which of the following is NOT typically included in the taking-off process?
- Measurement of dimensions from drawings
- Estimation of labor costs
- Assessing site conditions
- Calculating material quantities
Answer: B) Estimation of labor costs
Explanation:
Taking off primarily focuses on quantifying materials, while labor costs are typically estimated separately based on various factors.
Discuss this question