Which stage of project planning typically requires an approximate estimate?
86. Which stage of project planning typically requires an approximate estimate?
- Conceptual design
- Detailed design
- Post-construction evaluation
- Construction
Answer
The correct answer is: A) Conceptual design
Explanation
Approximate estimates are crucial during the conceptual design stage to assess project feasibility and budget constraints.