Which stage of project planning typically requires an approximate estimate?

86. Which stage of project planning typically requires an approximate estimate?

  1. Conceptual design
  2. Detailed design
  3. Post-construction evaluation
  4. Construction

Answer

The correct answer is: A) Conceptual design

Explanation

Approximate estimates are crucial during the conceptual design stage to assess project feasibility and budget constraints.