Which estimate involves the assessment of quantities of materials required for construction, such as concrete, steel, or bricks?
3. Which estimate involves the assessment of quantities of materials required for construction, such as concrete, steel, or bricks?
- Quantity estimate
- Supplementary estimate
- Detailed estimate
- Revised estimate
Answer
The correct answer is: A) Quantity estimate
Explanation
Determine the amounts of different building materials required based on project specifications and drawings. This process is known as quantity surveying or quantity estimation.