Which stage of the construction project is the Bill of Quantities typically prepared?
95. Which stage of the construction project is the Bill of Quantities typically prepared?
- Design stage
- Execution stage
- Planning stage
- Completion stage
Answer
The correct answer is: A) Design stage
Explanation
Working on architectural drawings and requirements, the Bill of Quantities is usually created during the design phase of a building project.