×

Multiple-Choice Questions

Web Technologies MCQs

Computer Science Subjects MCQs

Databases MCQs

Programming MCQs

Testing Software MCQs

Digital Marketing Subjects MCQs

Cloud Computing Softwares MCQs

AI/ML Subjects MCQs

Engineering Subjects MCQs

Office Related Programs MCQs

Management MCQs

More

Advertisement


Which type of estimate is prepared when additional work beyond the original project scope is required, leading to an increase in project costs?

5. Which type of estimate is prepared when additional work beyond the original project scope is required, leading to an increase in project costs?

  1. Detailed estimate
  2. Supplementary estimate
  3. Preliminary estimate
  4. Quantity estimate

Answer

The correct answer is: B) Supplementary estimate

Explanation

When unexpected events or more work crop up throughout the building process, supplemental estimates are made to account for them, which drives up project prices.

Comments and Discussions!

Load comments ↻






Copyright © 2024 www.includehelp.com. All rights reserved.