Which factor is NOT typically considered when estimating the cost of an R.C.C. Spun Pipe sluice?
92. Which factor is NOT typically considered when estimating the cost of an R.C.C. Spun Pipe sluice?
- Material cost
- Labor cost
- Equipment cost
- Weather conditions
Answer
The correct answer is: D) Weather conditions
Explanation
Weather conditions may affect construction timelines; they are not directly factored into cost estimates.