Which of the following factors is NOT considered when making an approximate estimate for a steel frame truss?

85. Which of the following factors is NOT considered when making an approximate estimate for a steel frame truss?

  1. Equipment costs
  2. Labor costs
  3. Material costs
  4. Detailed structural analysis

Answer

The correct answer is: D) Detailed structural analysis

Explanation

Approximate estimates typically do not involve detailed structural analysis but focus on material, labor, and equipment costs.