Which factor is NOT typically considered when tracking project timelines in civil engineering?
71. Which factor is NOT typically considered when tracking project timelines in civil engineering?
- Labor productivity
- Material availability
- Weather conditions
- Project profitability
Answer
The correct answer is: D) Project profitability
Explanation
Project profitability is not directly related to tracking project timelines, as it primarily concerns financial aspects such as costs and revenues.