Which factor is NOT typically considered when tracking project timelines in civil engineering?

71. Which factor is NOT typically considered when tracking project timelines in civil engineering?

  1. Labor productivity
  2. Material availability
  3. Weather conditions
  4. Project profitability

Answer

The correct answer is: D) Project profitability

Explanation

Project profitability is not directly related to tracking project timelines, as it primarily concerns financial aspects such as costs and revenues.