×

Multiple-Choice Questions

Web Technologies MCQs

Computer Science Subjects MCQs

Databases MCQs

Programming MCQs

Testing Software MCQs

Digital Marketing Subjects MCQs

Cloud Computing Softwares MCQs

AI/ML Subjects MCQs

Engineering Subjects MCQs

Office Related Programs MCQs

Management MCQs

More

Advertisement


Which of the following is a potential consequence of a low degree of accuracy in cost estimating?

22. Which of the following is a potential consequence of a low degree of accuracy in cost estimating?

  1. Enhanced project performance
  2. Increased stakeholder confidence
  3. Significant cost overruns
  4. Reduced project scope

Answer

The correct answer is: C) Significant cost overruns

Explanation

Budget problems and possible project delays might arise from cost overruns caused by inaccurate cost estimation.

Comments and Discussions!

Load comments ↻






Copyright © 2024 www.includehelp.com. All rights reserved.