Which of the following is a potential consequence of a low degree of accuracy in cost estimating?

22. Which of the following is a potential consequence of a low degree of accuracy in cost estimating?

  1. Enhanced project performance
  2. Increased stakeholder confidence
  3. Significant cost overruns
  4. Reduced project scope

Answer

The correct answer is: C) Significant cost overruns

Explanation

Budget problems and possible project delays might arise from cost overruns caused by inaccurate cost estimation.