When preparing a detailed estimate, what should be considered regarding the availability of materials?
12. When preparing a detailed estimate, what should be considered regarding the availability of materials?
- Distance to the nearest hospital
- Site security measures
- Source reliability
- Proximity to educational institutions
Answer
The correct answer is: C) Source reliability
Explanation
Source reliability is crucial for estimating costs, as unreliable material sources can lead to delays and increased expenses during construction.