Which estimating technique relies on historical data from similar projects to estimate costs?

2. Which estimating technique relies on historical data from similar projects to estimate costs?

  1. Bottom-up estimating
  2. Three-point estimating
  3. Analogous estimating
  4. Parametric estimating

Answer

The correct answer is: C) Analogous estimating

Explanation

Cost estimates from comparable projects are based on past data when using analogous estimation.