×

Multiple-Choice Questions

Web Technologies MCQs

Computer Science Subjects MCQs

Databases MCQs

Programming MCQs

Testing Software MCQs

Digital Marketing Subjects MCQs

Cloud Computing Softwares MCQs

AI/ML Subjects MCQs

Engineering Subjects MCQs

Office Related Programs MCQs

Management MCQs

More

Advertisement


Which estimating technique relies on historical data from similar projects to estimate costs?

2. Which estimating technique relies on historical data from similar projects to estimate costs?

  1. Bottom-up estimating
  2. Three-point estimating
  3. Analogous estimating
  4. Parametric estimating

Answer

The correct answer is: C) Analogous estimating

Explanation

Cost estimates from comparable projects are based on past data when using analogous estimation.

Comments and Discussions!

Load comments ↻






Copyright © 2024 www.includehelp.com. All rights reserved.