Which estimating technique relies on historical data from similar projects to estimate costs?
2. Which estimating technique relies on historical data from similar projects to estimate costs?
- Bottom-up estimating
- Three-point estimating
- Analogous estimating
- Parametric estimating
Answer
The correct answer is: C) Analogous estimating
Explanation
Cost estimates from comparable projects are based on past data when using analogous estimation.