Which type of estimate provides a detailed breakdown of all project costs?

7. Which type of estimate provides a detailed breakdown of all project costs?

  1. Revised estimate
  2. Quantity estimate
  3. Complete estimate
  4. Preliminary estimate

Answer

The correct answer is: C) Complete estimate

Explanation

All project costs, including those for supplies, labor, equipment, and overhead, are broken out in detail in the complete estimate.