×

Multiple-Choice Questions

Web Technologies MCQs

Computer Science Subjects MCQs

Databases MCQs

Programming MCQs

Testing Software MCQs

Digital Marketing Subjects MCQs

Cloud Computing Softwares MCQs

AI/ML Subjects MCQs

Engineering Subjects MCQs

Office Related Programs MCQs

Management MCQs

More

When a project undergoes significant changes, leading to adjustments in its cost, which type of estimate is prepared to reflect these alterations?

4. When a project undergoes significant changes, leading to adjustments in its cost, which type of estimate is prepared to reflect these alterations?

  1. Revised estimate
  2. Quantity estimate
  3. Complete estimate
  4. Preliminary estimate

Answer

The correct answer is: A) Revised estimate

Explanation

Revised estimates are prepared when substantial changes occur in a project, necessitating adjustments to the initial cost estimations to reflect the new scope or requirements.

Comments and Discussions!

Load comments ↻






Copyright © 2024 www.includehelp.com. All rights reserved.