Which chart represents the amount of work remaining in the project?

28. Which chart represents the amount of work remaining in the project?

  1. Burn-up chart
  2. Burn down chart

Answer: B) Burn down chart

Explanation:

Burn down chart describes the amount of work left/remaining in the project.