____ Process is a project's policies, procedures, and practices for producing a complete software product within certain cost, schedule, and quality constraints
7. ____ Process is a project's policies, procedures, and practices for producing a complete software product within certain cost, schedule, and quality constraints.
- Macro process
- Meta process
- Micro process
- None of the above
Answer: A) Macro process
Explanation:
Macro Process is a project's policies, procedures, and practices for producing a complete software product within certain cost, schedule, and quality constraints.