How many sequences of project checkpoints are used to synchronize stakeholders' expectations?
34. How many sequences of project checkpoints are used to synchronize stakeholders' expectations?
- 2
- 4
- 3
- 8
Answer: C) 3
Explanation:
Three sequences of project checkpoints are used to synchronize stakeholders' expectations: Major milestone, minor milestone, and status assessments.