Among the phases given below of the waterfall model which phase takes the longest time?

2. Among the phases given below of the waterfall model which phase takes the longest time?

  1. Integrating phase
  2. Analysis and requirement phase
  3. Testing phase
  4. Maintenance

Answer: D) Maintenance

Explanation:

Normally operation and maintenance phase is the longest life cycle phase. Maintenance involves correcting errors that were not detected in the early stage.