Which of the following is/are the artifact(s) in scrum?
25. Which of the following is/are the artifact(s) in scrum?
- Product backlog
- Sprint backlog
- Burndown Chart
- All of the above
Answer: D) All of the above
Explanation:
The following are the artifacts in the scrum -
- Product backlog
- Sprint backlog
- Burndown Chart